Installation of Drum Dryer at Naylor Nutrition!

  • Summer Le Conte
  • Feb 14, 2024
  • 1 min read



Progress is advancing smoothly at the Naylor Nutrition Factory located on Low Road. With the majority of civil works now completed, the focus has shifted to internal tasks and second fixing.


Over the past two months, crucial internal projects have been continuing to take delivery of machinery, shuttering and casting structural concrete plinths on piles to precise detail ready for installations, our team executed the task efficiently and meticulously.


Following the curing and setting process, the shuttering was removed, revealing a well-constructed plinth ready to support the 54-ton drum dryer which was craned in through the roof under controlled lift plans and co-ordination


Stay informed about our progress on current projects by following KCC Live.



 
 
 

Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.