top of page

Installation of Drum Dryer at Naylor Nutrition!




Progress is advancing smoothly at the Naylor Nutrition Factory located on Low Road. With the majority of civil works now completed, the focus has shifted to internal tasks and second fixing.


Over the past two months, crucial internal projects have been continuing to take delivery of machinery, shuttering and casting structural concrete plinths on piles to precise detail ready for installations, our team executed the task efficiently and meticulously.


Following the curing and setting process, the shuttering was removed, revealing a well-constructed plinth ready to support the 54-ton drum dryer which was craned in through the roof under controlled lift plans and co-ordination


Stay informed about our progress on current projects by following KCC Live.



19 views0 comments

Recent Posts

See All

Comentarios


Los comentarios se han desactivado.

© 2023 by Kirk Connection Construction. Powered and secured by Wix

bottom of page